Construction Change Order Template

Document an agreed change to a construction project's scope, price, or schedule so the original contract stays accurate.

  • General US template
  • PDF & Word
  • No account needed to start

4 sections up to 32 questions progress saved in your browser

CONSTRUCTION CHANGE ORDER

Change Order No.: ____________

Date: ____________

Project: ____________

Project address: ____________, ____________

Original contract date: ____________

Owner: ____________

Contractor: ____________

This Change Order modifies the construction contract between Owner and Contractor dated ____________ (the "Contract"). When signed by both parties, it becomes part of the Contract.

1. Description of Change

This change was requested by or results from: Owner.

Contractor will perform the following change in the work:


All work under this Change Order will be performed in accordance with the Contract documents, and all other terms of the Contract apply to it.

2. Change in Contract Sum

  • Original contract sum: ____________
  • Net change by previous change orders: $0.00
  • Contract sum before this Change Order: ____________
  • Amount of increase by this Change Order: ____________
  • New contract sum, including this Change Order: ____________

The change is priced as a lump sum, which includes all labor, materials, equipment, overhead, and profit for the changed work.

Payment. The amount of this change will be included in Contractor's next regular payment application and paid on the Contract's payment terms.

3. Change in Contract Time

This Change Order does not change the time for completion under the Contract.

4. Effect of This Change Order

The adjustments in contract sum and contract time stated above are full and final compensation for the changed work, including all direct and indirect costs, delays, disruption, acceleration, and impacts on other work. Contractor waives any further claim for additional money or time arising from this change, except for work that the parties later agree in writing falls outside its scope.

Except as modified by this Change Order and any earlier signed change orders, the Contract remains unchanged and in full force. No work described in this Change Order is authorized until it is signed by Owner and Contractor. This Change Order is governed by the laws of the State of ____________.

Signatures

What this Construction Change Order covers

The questionnaire has 4 sections. Follow-up questions only appear when your earlier answers make them relevant.

  • ProjectChange order number; Date of this change order; Project name; Project address; and more.
  • The ChangeWho requested the change; Describe the change in work; Reason for the change (optional); Drawings, specifications, or estimates attached (optional).
  • PriceOriginal contract sum; Net change from previous change orders; Contract sum before this change order; Effect of this change on price; and more.
  • ScheduleEffect on the completion date; Number of calendar days; New substantial completion date; Is this change order full settlement of all cost and time for the change; and more.

How to fill it out

  1. Work through the sections on the left. Each one asks a few questions in plain English.
  2. Watch the preview update. Anything you leave blank prints as a line to complete by hand.
  3. Choose PDF, Word or Print. Create a free account and start a trial when prompted.
  4. Sign the document, with witnesses or a notary if your state requires them for this kind of document.

Common questions

Can I fill out a Construction Change Order online?

Yes. Answer the questions above and the Construction Change Order is filled in as you type. You can preview the whole document before you download it as a PDF or Word file.

Is this Construction Change Order template free?

Filling it in and previewing it is free and needs no account. Downloading starts a 7-day trial for $0 or $1, then $49.95 per month until you cancel.

What do I need before I start?

Have the details this document asks for: project, the change, price, schedule. You can skip a question and come back, and blanks print as lines to complete by hand.

Is the finished Construction Change Order legally binding?

A document's effect depends on your state, your situation and proper signing, including witnesses or notarization where required. This template is a general US draft, not legal advice. Have an attorney review anything high-stakes.